EFFECTS IN PRACTICE
Daily practice under supervision - log (January)
Typical scope of activities performed within project management services. Go through the log or filter projects to see how I manage deadlines, budgets and quality in practice.
Date
Project "Client Facing Portal" - activities
Project "Analytics Web App" - activities
Jan 2
Thursday
Client Facing Portal
Inaugural and planning meeting of the Portal team. Goals for January (part of the team still on post-holiday leave, incomplete attendance). Daily stand-up of the Portal team. Backlog sorting under established goals. Short contact with the IT department regarding the dev environment - environment not ready, IT declares readiness for Jan 7.
Analytics Web App
Daily stand-up of the Analytics team (incomplete attendance after holidays). Initial sorting of the Analytics backlog for sprint planning. Scheduling Sprint 1 planning for Jan 7.
Jan 3
Friday
Client Facing Portal
Daily stand-up of the Portal team, 1:1 meeting with the Portal dev lead (return from leave, priority setting). Coordination with the UX team regarding page mockups. Short review of the Portal risk register (no changes since December).
Analytics Web App
Daily stand-up of the Analytics team, alignment with stakeholder on sprint priorities. Detailing stories and acceptance criteria for planning, short contact with the data team about data availability - one dataset not confirmed yet, risk under observation.
Jan 7
Tuesday
Client Facing Portal
Daily stand-up of the Portal team, re-directing the team to sprint goals after the break. Escalation to IT - dev environment still not ready, part of the team blocked. Temporary redirection of the team to tasks not requiring the environment to limit downtime. Status update after the break.
Analytics Web App
Analytics sprint planning (Sprint 1), sprint backlog sorting (task division and estimation by the team). Shortened team stand-up. Coordination with IT for Analytics environment needs. Sending sprint plan to stakeholders.
Jan 8
Wednesday
Client Facing Portal
Daily stand-up of the Portal team, dev environment unblocked before noon - confirmation from IT and redirecting the team to proper tasks. Short contact with support team about client feedback. 1:1 with the developer taking over the new module.
Analytics Web App
Daily stand-up of the Analytics team. Discussion of requirements with stakeholder. Updating project plan with the current sprint timeline. Short review of risk register - adding the risk of unconfirmed dataset.
Jan 9
Thursday
Client Facing Portal
Daily stand-up of the Portal team. Backlog grooming session (preparing next sprint) and notes distribution. Extended discussion with QA about test coverage gaps in one of the modules - setting a catch-up plan (most of the afternoon).
Analytics Web App
Daily stand-up of the Analytics team. Supporting requirement detailing with business. Contact with the data team - dataset confirmed, risk closed. Review of the budget consumption for the Analytics project.
Jan 10
Friday
Client Facing Portal
Daily stand-up of the Portal team. Weekly status update for stakeholders (short email, no major changes). Compilation of team work logs for the first week for project billing. Quiet administrative day. Low meeting volume.
Analytics Web App
Daily stand-up of the Analytics team. Progress check meeting to confirm sprint goal achievement. Short mid-sprint status update for stakeholder (email). Quiet day, low meeting volume.
Jan 13
Monday
Client Facing Portal
Daily stand-up of the Portal team, confirmation that sprint tasks are on track to close by Wednesday. Coordinating final QA testing of Portal deliverables. 1:1 with QA tester (overloaded with work, risk of bottleneck before sprint end).
Analytics Web App
Daily stand-up of the Analytics team. New developer in the Analytics team - onboarding on organization and project flow, coordination with IT for required accesses. Monitoring the start of his first tasks (most of the day). Identifying tasks at risk of delay and taking action. Confirming stakeholder availability for review next week.
Jan 14
Tuesday
Client Facing Portal
Daily stand-up of the Portal team, confirming sprint deliverables for tomorrow's review. Coordinating the deployment of features to the test environment for review. Finalizing Portal demo scenario. Reminding stakeholders about tomorrow's review. One task will not make it - decision to move to the next sprint and cancelling physical presentation.
Analytics Web App
Daily stand-up of the Analytics team. Backlog grooming session (preparing next sprint). 1:1 with the new developer after their first day (first impressions, blockers). Agreeing on sprint goals for the upcoming sprint with the product owner.
Jan 15
Wednesday
Client Facing Portal
Shortened stand-up of the Portal team. Portal sprint review (presentation of completed work. One item moved - discussion with stakeholders). Sprint retrospective of the Portal team. Documenting results and sending summary. Logging process improvements from retro. Closing sprint tasks in tracking system.
Analytics Web App
Daily stand-up of the Analytics team. Coordinating task reallocation within the team to reach sprint goals (new developer not yet at full capacity). Starting preparation of sprint review presentation. Assessing open risks before sprint end.
Jan 16
Thursday
Client Facing Portal
Shortened stand-up of the Portal team. Portal sprint planning (Sprint 2). Backlog sorting (task division and estimation by the team). Sending Sprint 2 scope to stakeholders. Applying retro improvements to process and tracking system.
Analytics Web App
Daily stand-up of the Analytics team. Confirming scope possible to finish by sprint end - some tasks at risk due to lower team capacity. Coordinating final test needs. Identifying two tasks to move to the next sprint.
Jan 17
Friday
Client Facing Portal
Daily stand-up of the Portal team. Monitoring the start of Sprint 2 tasks. Review of risks and timeline at sprint start. Meeting with stakeholder cancelled on their side at the last minute - rescheduled for Monday.
Analytics Web App
Daily stand-up of the Analytics team. Internal demo before review with the team. Finalizing presentation for the sprint review. QA coordination / confirming removal of reported defects.
Jan 20
Monday
Client Facing Portal
Daily stand-up of the Portal team, 1:1 with Portal dev lead on current issues. Coordinating QA testing of features. Rescheduled stakeholder meeting from Friday (short status update).
Analytics Web App
Daily stand-up of the Analytics team. Supervising final UAT testing of sprint deliverables. Creating review presentation and handover materials. Preparing retro points. Coordinating with data team to verify data correctness for presentation.
Jan 21
Tuesday
Client Facing Portal
Daily stand-up of the Portal team. Mid-sprint status meeting with stakeholders. Stakeholder requests urgent scope change (new regulatory requirement). Initial impact assessment - warning that change threatens sprint commitments.
Analytics Web App
Shortened stand-up of the Analytics team. Analytics sprint review (presentation of results, two tasks moved - discussing reasons with stakeholders). Sprint retrospective of the Analytics team. Documenting feedback and updating backlog. Sending sprint summary.
Jan 22
Wednesday
Client Facing Portal
Daily stand-up of the Portal team. Preparing backlog items for upcoming grooming. Short coordination of cross-team dependencies. Waiting for stakeholder decision on priority of change request - grooming day in hold mode.
Analytics Web App
Analytics sprint planning (Sprint 2). Sprint backlog sorting (task division by the team). Shortened team stand-up. Moving two rollover tasks to Sprint 2. Sending plan to stakeholders. Applying retro improvements to process.
Jan 23
Thursday
Client Facing Portal
Daily stand-up of the Portal team, urgent discussion of change request with the team and effort estimation (extended session, most of the morning). Escalating scope conflict - negotiations with stakeholders on which tasks drop out of the sprint to fit the new requirement. Hard conversation about timeline and cost impact. Agreeing on compromise and dropping two tasks from the sprint. Adjusting plan and sprint scope. Backlog reprioritization. Re-negotiating timeline feasibility with the dev lead. Short note to finance department about possible change impact on billing.
Analytics Web App
Daily stand-up of the Analytics team. Detailing new stories with stakeholders. Coordinating data team for upcoming features. PM engaged mostly on Portal (scope change escalation) - Analytics day limited to essential minimum.
Jan 24
Friday
Client Facing Portal
Daily stand-up of the Portal team. Backlog sorting session after scope change. Risk register review after the change. Coordinating release plans with IT for the upcoming release. Short update to stakeholder on change implementation status.
Analytics Web App
Daily stand-up of the Analytics team. Mid-sprint progress update for stakeholder. Coordinating with data team to confirm data pipeline stability. Checking early user feedback on features.
Jan 27
Monday
Client Facing Portal
Daily stand-up of the Portal team. Coordinating final QA testing of features. Finalizing deployment plan with IT. Coordinating release notes preparation. Checking support readiness for new features. Coordinating with external auth provider - delay on their side, risk for deployment.
Analytics Web App
Daily stand-up of the Analytics team. Coordinating team integration and testing. Scheduling grooming for next sprint. One Analytics developer on sick leave (L4) - coordinating task reallocation, risk for timeline. Mid-sprint risk review.
Jan 28
Tuesday
Client Facing Portal
Daily stand-up of the Portal team. Supervising completion of final dev tasks. Coordinating final UAT testing. Internal demo before review. Confirmation of auth delivery from external provider. Pre-deployment testing. Finalizing release notes. Closing completed tasks in system.
Analytics Web App
Daily stand-up of the Analytics team. Alert from data team about data discrepancy in final test results - halting readiness confirmation. Half the day on coordinating data team diagnostics (under reduced capacity - one developer on L4). Informing stakeholders about the issue and possible timeline impact. Initial risk assessment showing that the problem might have a broader source - probable sprint delay.
Jan 29
Wednesday
Client Facing Portal
Shortened stand-up of the Portal team. Portal sprint review (presentation of completed work). Sprint retro of the Portal team. Documenting results and sending to stakeholders. Setting next planning date (February 3). Coordinating with IT for production launch (go-live) next day.
Analytics Web App
Daily stand-up of the Analytics team. Supervision and coordination of deep diagnostics by data team - data shows discrepancy has a broader source than a single record (most of the day on coordination). Decision to drop part of sprint scope and move to next sprint. Hard conversation with stakeholder about delay and limited review scope. Backlog grooming postponed due to crisis.
Jan 30
Thursday
Client Facing Portal
Day of two parallel critical issues (Portal go-live and Analytics data failure) - part of Portal tasks delegated or postponed due to lack of time. Supervising production launch (go-live) of Portal. Coordinating smoke tests and post-deployment monitoring. Readiness for rollback decision. Minor bugs found after launch - coordinating hotfix. Priority competing with Analytics escalation. Short note to stakeholders about release completion (full report postponed to next day due to lack of time).
Analytics Web App
Daily stand-up of the Analytics team. Parallel Portal go-live - PM splits attention between two critical issues. Meeting with data team about workaround and coordinating its implementation. Confirming full solution will not fit in this sprint - formal rollover to next sprint with consequences. Escalation to high-level stakeholder - loss of trust in timeline. Setting recovery plan. Re-directing team after crisis.
Jan 31
Friday
Client Facing Portal
Daily stand-up of the Portal team. Completing and sending full Portal post-deployment report (postponed from Thursday). Monthly status report for Portal. Review of project metrics for January. Compiling Portal team work logs for January for billing. Preparing data for monthly invoicing.
Analytics Web App
Daily stand-up of the Analytics team. Confirming scope moved to next sprint and its impact on plan. Monthly status report for Analytics (with noted delay and recovery plan). Review of project metrics for January - below target due to data issue. Status update for stakeholders on progress and recovery steps. Preparing invoicing data.